Quantcast

McHenry Times

Monday, November 4, 2024

PROJECT UPDATES POSTED: PLAYGROUND SAFETY SURFACING PLUS LAPINS AND BRIGHTON OAKS PLAYGROUNDS

Playground Surfacing

Update: Aug 26, 2022

Woodscreek: The surfacing was installed and is curing. Safety testing and inspection is upcoming. We hope to have the park open soon.

Veteran Acres: The surfacing work is in progress. The rain may cause delays. Once the surfacing is installed, safety testing and site inspection will follow.

Woodland Estates: The surfacing did not cure properly and did not pass inspection. The manufacturer is working with the contractor to remedy the issue in the next few weeks.

 

Kamijima Playground

Update: Aug 26, 2022

We are waiting on delivery of the play equipment to start the project.

Brighton Oaks Playground

 

Update: Aug 26, 2022

We are waiting on delivery of a swing. A site inspection is scheduled for next week. The playground will be open soon.

 

Lapins Playground

Update: Aug 26, 2022

The contractor is working to finish the punch list items. The playground will be open soon!

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS