Playground Surfacing
Update: Aug 26, 2022
Woodscreek: The surfacing was installed and is curing. Safety testing and inspection is upcoming. We hope to have the park open soon.
Veteran Acres: The surfacing work is in progress. The rain may cause delays. Once the surfacing is installed, safety testing and site inspection will follow.
Woodland Estates: The surfacing did not cure properly and did not pass inspection. The manufacturer is working with the contractor to remedy the issue in the next few weeks.
Kamijima Playground
Update: Aug 26, 2022
We are waiting on delivery of the play equipment to start the project.
Brighton Oaks Playground
Update: Aug 26, 2022
We are waiting on delivery of a swing. A site inspection is scheduled for next week. The playground will be open soon.
Lapins Playground
Update: Aug 26, 2022
The contractor is working to finish the punch list items. The playground will be open soon!
Original source can be found here.